Understand
OSP Map
Every part of aerial and underground plant, where it sits and how the pieces connect. Tap a part for what it is, what to inspect and which SOP step covers it.
Layers
Legend
- AE PlantSolid blue lines: strand and lashed cable
- UG PlantDashed orange line
- SplicingViolet diamond, "SC"
- DropsDotted line
- PowerThin solid red line
- Existing UtilitiesDash-dot line with letter code
- LocatesShort paint dashes
- Buried DropDotted orange line
- Bore PathPlanned: thin long dash. Actual: UG dash
- SteelGuys, hardware and anchor rods
- DimensionClearance or separation, per NESC / owner spec
- KeynoteNumbered callout, listed below the map
- HaloSelected or highlighted part
Existing Utilities
- Water
- Gas
- Sewer
- Electric
- Communications
Locate Paint (APWA)
- OrangeCommunications
- RedElectric
- YellowGas, oil, steam
- BluePotable water
- GreenSewer and drain
- PurpleReclaimed water
- PinkTemporary survey
- WhiteProposed excavation
Pinch, Ctrl + scroll or + and − to zoom. Drag or arrow keys to pan. 0 resets.
- Keynote 1Supply Space, Power at the Top of the Pole
- Keynote 2Communication Worker Safety Zone
- Keynote 3Communication Space: Existing Attacher above the New Strand
- Keynote 4Down Guy, Holding the Dead-Ended Strand
- Keynote 5Yellow Guy Guard
- Keynote 6Anchor Rod in Line with the Guy
- Keynote 7Messenger Strand, Sagged Pole to Pole
- Keynote 8Fiber Cable Lashed to the Strand
- Keynote 9Multiport Service Terminal
- Keynote 10Aerial Drop to the House
- Keynote 11Slack Loop in a Figure-8 on Snowshoes
- Keynote 12Aerial Splice Closure
- Keynote 13Riser: Aerial Becomes Underground
- Keynote 14Midspan Clearance over the Road
- Keynote 15Handhole with Slack Coil
- Keynote 16Tracer Wire and Test Point
- Keynote 17Directional Bore below the Road and Utilities
- Keynote 18Tolerance Zone Either Side of the Gas Line
- Keynote 19Pothole Exposing the Gas Line
- Keynote 20Locate Paint and Flags
- Keynote 21Pedestal
- Keynote 22Buried Drop to the House
- Keynote 23Restoration over the Trench
- Keynote 24Warning Tape above the Ducts
- Keynote 25Duct Bank in the Trench
Every Component
Pole and Structure
- Utility PoleWood, steel or concrete pole that carries power at the top and communication attachments below it.Views: Profile · Plan · Pole
- Pole Tag and BirthmarkThe owner’s number tag and the manufacturer’s birthmark showing class, height, treatment and year.Views: Pole
- Communication Worker Safety ZoneRequired separation between supply facilities and communication attachments (NESC, owner spec).Views: Profile · Pole
Power and Grounding
- Supply SpaceUpper section of the pole for power conductors and equipment; only qualified electrical workers work there.Views: Profile · Pole
- Neutral and SecondaryGrounded power conductor, often near the bottom of the supply space; measure separation from the lowest supply facility.Views: Profile · Pole
- Vertical Ground and BondingThe pole’s vertical ground wire; the strand is bonded to it per NESC and owner spec.Views: Pole
Aerial Plant
- Communication SpacePole section below the safety zone for telecom attachments, spaced per the owner’s standard.Views: Profile · Pole
- Messenger StrandGalvanized steel strand tensioned pole to pole that carries the lashed fiber cable.Views: Profile · Plan · Pole
- Lashed Fiber CableFiber cable bound to the messenger strand with a spiral of lashing wire.Views: Profile · Plan · Pole
- Expansion LoopCable loop formed at a pole to absorb movement, where the owner requires it.Views: Profile · Pole
- Corner Pole and Bisect GuyAngle pole guyed on the bisector of the line angle.Views: Plan
- SnowshoePair of curved strand brackets that store a slack loop without kinking the cable.Views: Profile · Plan · Pole
- Aerial Slack LoopCable stored on the strand for future splicing, repair or relocation.Views: Profile · Plan
- Terminal Tail CoilStored coil of the terminal’s tail cable, held in a bracket on the pole or strand.Views: Pole
- Cable TagIdentification tag on the cable at each pole that names the owner and the cable.Views: Pole
Hardware and Guying
- Through-BoltBolt through the pole at the engineered attachment height that carries the strand clamp.Views: Pole
- Strand ClampSuspension clamp on the through-bolt that holds the messenger strand to the pole.Views: Pole
- Extension Arm or StandoffBracket that holds the strand away from the pole face to gain clearance.Views: Pole
- Lashing Wire ClampClamp that anchors the end of the lashing wire on the strand at each pole.Views: Pole
- Strand Dead-EndTermination of the strand at a terminal pole, guyed against the pull.Views: Profile · Pole
- Down GuySteel strand from the pole to an anchor that balances the line’s unbalanced tension.Views: Profile · Plan · Pole
- Preformed Guy GripHelical dead-end that terminates the guy strand at the pole and at the anchor.Views: Pole
- Guy GuardYellow marker on the lower guy where people or vehicles could walk or drive into it.Views: Profile · Pole
- Guy Strain InsulatorInsulating link placed in a guy where the power owner or NESC requires one.Views: Pole
- Anchor and Anchor RodScrew, expanding, plate or rock anchor set below grade in line with the guy load.Views: Profile · Plan · Pole
- Span and Sidewalk GuysGuying used when an in-line down guy and anchor cannot be placed.Views: Plan
Aerial to Underground
- RiserU-guard and conduit on the pole where cable moves between aerial and underground.Views: Profile · Plan · Pole
Underground Plant
- HDPE ConduitContinuous plastic duct placed by boring, plowing or trenching to carry fiber underground.Views: Profile · Plan
- Innerduct and MicroductSmaller ducts inside a conduit that create separate pathways or carry air-blown cable.Views: Handhole
- Duct BankSeveral ducts placed together in one trench, sometimes encased in concrete.Views: Profile
- Tracer Wire and Test PointLocatable wire placed with non-metallic duct where specified (owner spec) and tested for continuity at each enclosure.Views: Profile · Handhole
- Warning TapeBuried marking tape placed above the duct in an open trench to warn future diggers.Views: Profile
- HandholeBelow-grade box with a load-rated lid for cable access, slack storage and splicing.Views: Profile · Plan · Handhole
- Handhole Lid MarkingLid marking that names the owner and use and shows the load rating.Views: Handhole
- Vault or ManholeBelow-grade enclosure large enough to enter; confined-space rules apply.Views: Plan
- PedestalAbove-grade enclosure that houses buried splices or drop terminals.Views: Profile · Plan
- FlowerpotSmall grade-level enclosure for drop terminals and short slack.Views: Plan
- Handhole Slack CoilCable stored in a coil inside a handhole or vault, within bend radius.Views: Handhole
- Directional Bore PathPlanned and actual pilot-bore path between the entry and exit pits, passing under existing utilities.Views: Profile · Plan · Bore
- Entry PitExcavation where the drill head enters the ground, with drilling fluid containment.Views: Bore
- Exit PitExcavation where the drill head surfaces and the pullback string is assembled.Views: Bore
- Drilling Fluid and RecoveryFluid that carries cuttings and holds the hole open; contained and disposed of per regulations.Views: Bore
- PotholeVacuum or hand excavation that exposes an existing utility before the bore crosses it.Views: Profile · Plan · Bore
- Micro-TrenchNarrow saw-cut trench in pavement for microduct, sealed after placement.Views: Plan
Equipment
- HDD RigDirectional drill, anchored to the ground, with electrical strike protection.Views: Bore
- Drill RodsRods added one at a time behind the drill head; each rod is a common reading interval unless the owner sets another.Views: Bore
- Drill Head and SondeSlant-face bit carrying a transmitter that reports depth, pitch and roll to the locator.Views: Bore
- Walkover LocatorReceiver carried over the bore head to read its position and depth and guide steering.Views: Bore
- BackreamerTool pulled back through the pilot hole to enlarge it for the product.Views: Bore
- SwivelRotating link that keeps the drill string’s rotation from twisting the conduit.Views: Bore
- Breakaway LinkSacrificial link that breaks before the pull stretches any conduit past its safe pull strength.Views: Bore
- Pulling Head or GripFitting that connects the pullback string to the conduit or conduit bundle.Views: Bore
- Conduit Reel and TrailerReel on a trailer that pays out conduit in line with the bore during pullback.Views: Bore
- Splicing WorkstationTrailer, van or tent that gives the splicer a clean, dry, lit workspace.Views: Profile
- OTDR with Launch CableInstrument that maps loss and reflectance along a fiber; launch and receive cables reveal end connectors.Views: Handhole
Splicing
- Aerial Splice ClosureSealed closure on the strand where fibers are spliced and stored.Views: Profile · Plan
- Multiport Service TerminalHardened terminal with connectorized ports that customer drops plug into.Views: Profile · Plan · Pole
- Underground Splice ClosureSealed splice closure mounted on a bracket in a handhole or vault, with slack to lift it out.Views: Handhole
- Closure InteriorExpress basket, splice trays, strength-member clamps, grounding and seals inside a closure.Views: Handhole
- Splice TrayTray that holds splice protection sleeves and routes fibers within bend radius.Views: Handhole
- Buffer Tubes and Color CodeColor-coded tubes and fibers identified with the TIA-598 sequence.Views: Handhole
- Fiber Distribution HubCabinet with splitters that links feeder fibers to distribution fibers.Views: Plan
- Splitter ModulePassive optical splitter that divides one feeder fiber among several distribution fibers.Views: Plan
Drops
- Aerial DropDrop cable from a terminal to the building, held with drop clamps at each end.Views: Profile · Plan
- Buried DropDrop cable or duct from a pedestal or handhole to the building.Views: Profile · Plan
Locates
- Locate MarksAPWA-colored paint and flags marking the approximate location of buried facilities.Views: Profile · Plan · Bore
- White-LiningWhite paint dashes, like locate marks, down the centerline of the intended bore path so locators know what to mark.Views: Plan
Existing Utilities
- Water MainExisting potable water line, marked in APWA blue; drawn with the letter code W.Views: Profile · Plan · Bore
- Gas MainExisting gas line, marked in APWA yellow; on a strike, evacuate and call 911, then the utility, per your emergency plan.Views: Profile · Plan · Bore
- Sewer Main and LateralSewer main and service laterals, marked in APWA green; laterals are often unmarked and a crossbore risk.Views: Profile · Plan · Bore
- Underground PowerBuried electric line, marked in APWA red; an electrical strike risk for HDD.Views: Plan · Bore
- Existing CommunicationsOther companies’ buried communication lines, marked in APWA orange.Views: Plan
Clearances and Site
- Midspan ClearanceHeight of the cable’s lowest point over roads, drives and walks (NESC Table 232-1, owner spec).Views: Profile
- Surface RestorationBackfill, compaction and surface repair to the permit and owner specification.Views: Profile
- Tolerance ZoneBand either side of a locate mark where you dig only with the methods state law allows, typically hand tools or vacuum excavation.Views: Profile · Bore
- Road CrossingWhere the route crosses a road: bored under it, or spanned over it with the required clearance.Views: Profile · Plan