UG Underground Operations · 13 Steps

Underground Operations

Underground OSP construction step by step: permits, locates, potholing, directional boring, enclosures, cable placement and restoration.

Steps in Order

No checklist ticks saved on this device yet.

  1. UG-01

    Permits and Right-of-Way

    Get written permission for every work location, and carry the permit conditions on site, before any excavation starts.

    8 steps · 1 hold point

  2. UG-02

    Pre-Construction Survey, Staking and White-Lining

    Walk the route, document existing conditions, stake pits and enclosures, and white-line the dig area before anyone excavates.

    8 steps · 1 hold point

  3. UG-03

    One-Call Locates (811) and Ticket Management

    Get every buried facility marked before you dig, verify the marks on site, and keep a valid ticket for every day of work.

    9 steps · 1 hold point

  4. UG-04

    Potholing (Daylighting)

    Expose every utility the bore will cross or closely parallel, and record its true depth, size and direction before drilling.

    7 steps · 1 hold point

  5. UG-05

    Bore Planning and Rig Setup

    Plan a bore path that meets cover and clearance, then set up a safe, contained site with a calibrated locator and a tested strike system.

    8 steps · 1 hold point

  6. UG-06

    Pilot Bore and Tracking

    Drill the pilot hole on the planned path, stay clear of existing utilities and keep an accurate bore log.

    8 steps · 2 hold points

  7. UG-07

    Reaming and Pullback

    Enlarge the pilot hole and pull the conduit or conduit bundle in through a swivel and breakaway link, without damaging or overstressing it.

    8 steps · 1 hold point

  8. UG-08

    Other Placement Methods

    Choose open trench, plowing or micro-trenching when boring is not the best fit, and apply each method's key controls.

    7 steps · 2 hold points

  9. UG-09

    Handholes, Vaults and Pedestals

    Set enclosures level and at grade with the right load rating, bring ducts and tracer wire in cleanly, and give safe access.

    7 steps · 1 hold point

  10. UG-10

    Duct Proving and Pull Tape

    Prove every duct is clear and round, install footage-marked pull tape where specified, and plug every duct end before cable placement.

    5 steps · 1 hold point

  11. UG-11

    Cable Placement Underground

    Pull or blow fiber into duct without exceeding tension or bend limits, and store the right slack in the right places.

    8 steps · 2 hold points

  12. UG-12

    Restoration and Cleanup

    Dispose of spoils and drilling fluid legally, backfill and compact, and restore every surface to the permit specification.

    7 steps · 1 hold point

  13. UG-13

    Documentation and Closeout

    Hand over as-builts, test results and permit closeouts that match what is actually in the ground.

    6 steps · 1 hold point