One-Call Locates (811) and Ticket Management

Get every buried facility marked before you dig, verify the marks on site, and keep a valid ticket for every day of work.

WatchChecklistOn the Map

Crew

  • Foreman
  • Permitting Coordinator or Project Manager
  • Utility Locators
  • Private Locator

Hazards

  • Gas Line Strike
  • Electrical Strike
  • Damage to Communication and Water Lines
  • Unmarked Private and Non-Member Lines

UG-03 · OSP Hub Shorts

Watch the Video

Purpose

Make sure every buried facility on the route is marked before excavation, and that your locate ticket is valid for every day you dig. The ticket is your legal protection and the first control against a gas or electric strike. Digging without a valid ticket breaks state law and puts the crew and the public at risk.

When to Do It

  • Trigger: white-lining is done (UG-02) and you know when the crew will start.
  • Timing: submit before digging, at least the notice period your state requires: commonly two to three full business days; varies by state.
  • Prerequisites: white-lined dig areas and an accurate description of the work.
  • Previous step: UG-02 Pre-Construction Survey, Staking and White-Lining.
  • Next step: UG-04 Potholing (Daylighting).

Roles

  • Foreman: submits or confirms the ticket, verifies marks on site, and stops work when marks are missing or the ticket is not valid.
  • Permitting coordinator or project manager: tracks ticket numbers, renewals and expiration dates across the job.
  • Utility locators: mark their member facilities.
  • Private locator: marks private and non-member lines.

Equipment and Materials

  • One-call ticket from the state one-call center (dial 811 or file online).
  • Camera with date and time stamp.
  • White marking paint and white flags.
  • Ticket tracking log or spreadsheet: ticket number, area, start date, expiration date, responses.

Safety

Procedure

  1. Submit the ticket to the state one-call center before digging, at least the notice period your state requires: commonly two to three full business days; varies by state.
  2. Describe the work accurately so locators mark the right area:
    • Location and the white-lined area.
    • Method: directional boring, plowing or trenching.
    • Expected depth and duration of the work.
  3. Wait for the legal start time. Confirm every member utility has responded, using the positive response system where your state has one.
  4. On site, compare the locate marks with the ticket.
    • Check each expected utility against the ticket’s member list.
    • Look for unmarked indicators: meters, valve boxes, cleanouts, pedestals, risers.
    • Photograph the marks before work starts.
  5. Request re-marks for missing, faded or conflicting marks, per your state one-call law. Do not dig until each one is resolved.
  6. Treat marks as approximate horizontal location only. Respect the tolerance zone. Measure from each outside edge of the facility as marked, including any width or size shown at the mark: commonly the facility width plus 18 to 24 inches either side; set by state law. Inside it, dig only with the methods your state law allows, typically non-powered hand tools or vacuum excavation.
  7. Track ticket expiration and renew before it lapses; ticket life and renewal rules vary by state. The ticket must cover where you dig today.
  8. Use a private locator for private and non-member lines, such as sewer laterals, irrigation and private electric.
  9. Request new marks after rain, grading or anything else that removes or moves the marks, per your state one-call law.

Hold Points

Records to Keep

  • Ticket numbers, dig areas and expiration dates.
  • Positive responses from every member utility.
  • Dated photos of the marks before work.
  • Re-mark requests and their responses.
  • Ticket renewals.

Common Mistakes

  • Digging on an expired or wrong ticket. Check the ticket number and area every morning.
  • Assuming marks show depth. They do not. Depth comes from potholing (UG-04).
  • Relying on 811 for sewer laterals. Laterals are often not marked and are a crossbore risk. Arrange a private locate or a camera inspection.
  • Not re-marking after rain or grading. Faded or graded-over marks are not marks.
  • Calling an emergency locate to save schedule. It misuses the system and can break state law.

Standards and References

  • State one-call law: notice periods, tolerance zones, ticket life and marking rules vary by state.
  • 811: the national number that reaches your state one-call center.
  • The Permit Directory: the 811 summary of each state’s one-call law, and its one-call center where listed.
  • CGA Best Practices: locating and excavation practices.
  • APWA uniform color code: the American Public Works Association (APWA) uniform color code: red electric, yellow gas and oil, orange communications, blue potable water, green sewer, purple reclaimed water, pink survey, white proposed excavation.
  • 29 CFR 1926 Subpart P: excavation rules, including contacting utilities, finding their exact location and protecting exposed installations (1926.651(b)).

On the Map

  • Locate Marks: paint and flags in the APWA color code showing the approximate location of buried facilities.
  • White-Lining: the white dashes you painted down the bore path’s centerline for the locators.
  • Tolerance Zone: the band either side of the marked facility, measured from its outside edges, where you dig only with the methods state law allows (typically non-powered hand tools or vacuum excavation).
  • Water Main: existing potable water, marked blue.
  • Gas Main: existing gas, marked yellow.
  • Sewer Main and Lateral: sewer, marked green; laterals are often unmarked.

Not applicable: no FAHMY tool covers locate tickets.

UG-03 · Field Checklist

Checklist

0/10items ticked

Tick each procedure step and hold point as the crew completes it. Ticks stay on this device only. They are a personal aid, not a hold-point release or a project record; follow the owner’s sign-off process.

Procedure
Hold Points

OSP Map · Plan View

On the Map

Open the map
  • Locate MarksAPWA-colored paint and flags marking the approximate location of buried facilities.
  • White-LiningWhite paint dashes, like locate marks, down the centerline of the intended bore path so locators know what to mark.
  • Tolerance ZoneBand either side of a locate mark where you dig only with the methods state law allows, typically hand tools or vacuum excavation.Drawn in the route profile
  • Water MainExisting potable water line, marked in APWA blue; drawn with the letter code W.
  • Gas MainExisting gas line, marked in APWA yellow; on a strike, evacuate and call 911, then the utility, per your emergency plan.
  • Sewer Main and LateralSewer main and service laterals, marked in APWA green; laterals are often unmarked and a crossbore risk.

Report an Issue

Spotted something wrong or out of date? Emailfeedback@fahmy.iowith the step and version (UG-03, v1.0.0) and what you saw in the field.

FAHMY is a reference, not a substitute for owner specifications, the authority having jurisdiction, manufacturer instructions, training or qualified supervision. Follow your employer's safety program and all applicable laws.

Operations

More

Theme

Sunlight is maximum contrast for direct sun. Auto follows your device.