AE Aerial Operations · 12 Steps

Aerial Operations

Aerial OSP construction step by step: pole attachment applications, make-ready, framing, anchors and guys, strand, lashing, slack, terminals and inspection.

Steps in Order

No checklist ticks saved on this device yet.

  1. AE-01

    Pole Attachment Applications

    Get written authorization from every pole owner, pole by pole, before any crew works on or attaches to a pole.

    7 steps · 1 hold point

  2. AE-02

    Field Survey and Make-Ready Engineering

    Survey every pole and span, set an attachment height that meets NESC and owner rules, run pole loading and list the make-ready.

    6 steps · 1 hold point

  3. AE-03

    Make-Ready Execution and Coordination

    Sequence and coordinate power, attacher and pole work, then verify every pole with photos before framing starts.

    5 steps · 1 hold point

  4. AE-04

    Site Safety and Traffic Control for Aerial Work

    Hold the tailboard, set traffic control, inspect lifts and poles, test for voltage and stay clear of power before any aerial work.

    7 steps · 1 hold point

  5. AE-05

    Framing Poles

    Install through-bolts, strand clamps and arms at the engineered height, bond to the pole ground and keep the climbing space clear.

    7 steps · 1 hold point

  6. AE-06

    Anchors

    Set anchors that hold the designed load, in line with the guy, at the designed lead, with a valid locate ticket.

    6 steps · 2 hold points

  7. AE-07

    Down Guys and Guy Guards

    Install guys that balance the line's unbalanced tension, tension them before the strand and guard them for the public.

    8 steps · 1 hold point

  8. AE-08

    Strand Placement and Tensioning

    Pull strand, dead-end one terminal, tension from the far end to the owner's sag chart, dead-end it, then bond and check clearances.

    11 steps · 4 hold points

  9. AE-09

    Cable Placement and Lashing

    Pull fiber through cable blocks within its tension rating and bend radius, then lash it tight to the strand and clamp it at every pole.

    6 steps · 2 hold points

  10. AE-10

    Slack Storage Loops and Snowshoes

    Store the specified slack at the design locations in a figure-8 loop between snowshoes that keeps bend radius, clear of climbing space and power.

    5 steps · 1 hold point

  11. AE-11

    Terminal Coils, Closures, Drops and Risers

    Mount closures, terminals, drops and risers so they are serviceable, protected, bonded and clear of roads and the climbing space.

    5 steps · 2 hold points

  12. AE-12

    Labeling, Inspection and As-Builts

    Tag the cable at every pole, verify heights and clearances after sag settles, clear the punch list and submit as-builts that match the field.

    5 steps · 1 hold point