AE Aerial AE-12 Step 12 of 12
Labeling, Inspection and As-Builts
Tag the cable at every pole, verify heights and clearances after sag settles, clear the punch list and submit as-builts that match the field.
Crew
- Foreman
- Lineworker
- Inspector or Owner Representative
- OSP Designer or Drafter
- Project Manager
Hazards
- Contact with Energized Facilities
- Traffic
- Falls during Corrections
Purpose
Leave a clean, labeled, inspected line and records that match it. The owner, the next attacher and every future repair crew rely on the tags and the as-builts. An as-built copied from the design sends the next crew to a closure that is not there, or a slack loop that was never stored.
When to Do It
- After all aerial work in a section is complete (AE-11 Terminal Coils, Closures, Drops and Risers).
- Clearance checks wait until the sag has settled after lashing (per owner spec).
- The owner’s post-construction inspection follows the attachment agreement (AE-01).
- This is the last aerial step. Splicing and testing follow in the splicing SOPs (SPL-11 Testing and Acceptance).
Roles
- Foreman: tags the cable, runs the final check, photographs the line and clears the punch list.
- Lineworker: makes corrections aloft.
- Inspector or owner representative: walks the line for the post-construction inspection and issues the punch list.
- OSP designer or drafter: turns field redlines into as-builts.
- Project manager: submits as-builts and closes out with the owner.
Equipment and Materials
- Cable tags in the format the owner specifies.
- Non-conductive height measuring stick or laser rangefinder (29 CFR 1910.268(n)(13)).
- Camera.
- Field tablet or prints for redlines.
- Bucket truck for any corrections.
Safety
Procedure
- Tag the cable at every pole per owner spec.
- Use the owner’s tag format and position, so a lineworker can identify your cable from the bucket.
- After the sag settles, verify attachment heights and midspan clearances.
- Check the midspan clearance over roads, driveways and walks (per National Electrical Safety Code (NESC) Table 232-1) and the separations at each pole.
- Correct anything out of spec now, before the owner finds it.
- Photograph each pole before and after, and every closure, terminal and slack location.
- Walk the line with the owner for the post-construction inspection when the owner requires one.
- Clear every item on the punch list and send proof of each fix.
- Submit as-builts that show what was built, from the field redlines:
- attachment heights;
- strand and cable footage;
- slack locations and lengths;
- closures and terminals;
- guys and anchors.
Hold Points
Records to Keep
- Before and after photos of every pole.
- Photos of every closure, terminal and slack location.
- Final measured attachment heights and midspan clearances.
- The owner’s inspection report and proof that each punch list item was closed.
- As-builts as submitted, with the date and the owner’s acceptance.
Print the blank punch list for the final walk and the closeout package checklist to gather these records for the owner.
Common Mistakes
- Missing tags. An untagged cable can be treated as unauthorized or abandoned.
- No after photos. Without them, you cannot prove what you left when a dispute comes up.
- As-builts copied from the design. As-builts must come from field redlines and measurements.
- Checking clearances before the sag settles, then finding low spans later.
Standards and References
NESC (IEEE C2)Table 232-1 for vertical clearances.- Owner construction standards for tags, inspection and as-built requirements.
29 CFR 1910.268for work near power.- OSHA 29 CFR Part 1926 for construction work, which 29 CFR 1910.268 excludes (1910.268(a)(2)(i)). Your employer’s safety program says how to comply.
MUTCD Part 6for traffic control during midspan measurements and corrections over roads.
On the Map
- Cable Tag: the identification tag on the cable at each pole.
- Midspan Clearance: the clearance of the cable’s lowest point, checked after sag settles.
- Utility Pole: every pole gets a tag and before and after photos.
Related Tools
Not applicable: no FAHMY tool covers labeling, inspection or as-builts.
AE-12 · Field Checklist
Checklist
0/6items ticked
Tick each procedure step and hold point as the crew completes it. Ticks stay on this device only. They are a personal aid, not a hold-point release or a project record; follow the owner’s sign-off process.
OSP Map · Pole Detail
On the Map
- Cable TagIdentification tag on the cable at each pole that names the owner and the cable.
- Midspan ClearanceHeight of the cable’s lowest point over roads, drives and walks (NESC Table 232-1, owner spec).Drawn in the route profile
- Utility PoleWood, steel or concrete pole that carries power at the top and communication attachments below it.