Contractor Name and Logo

  • Project name
  • Owner
  • Contractor
  • Work order or job number
  • Area, route or segment
  • Package submitted by
  • Date submitted

Closeout Checklist

Lines from the Close Out stage checklist

  • Field redlines turned into as-built drawings and GIS updates
  • Bore logs and enclosure GPS locations included in the underground as-builts
  • Tracer wire continuity tested end to end and recorded
  • Test and splice reports compiled by fiber
  • Splice matrix updated with every field change
  • Punch list walked and cleared with the owner or inspector
  • Permits closed and restoration accepted
  • Pole attachment records updated with heights and transfers
  • Final quantities reconciled against the BOM for invoicing

Aerial Records

Lines from AE-12 Records to Keep

  • Before and after photos of every pole.
  • Photos of every closure, terminal and slack location.
  • Final measured attachment heights and midspan clearances.
  • The owner's inspection report and proof that each punch list item was closed.
  • As-builts as submitted, with the date and the owner's acceptance.

Underground Records

Lines from UG-13 Records to Keep

  • As-built drawings and GIS data.
  • Bore logs, pothole logs and redlines.
  • Tracer wire continuity test results.
  • Pull tape and cable footage at each enclosure.
  • Final inspection sign-offs and permit closure letters.
  • Photo archive and locate tickets.

Splicing Records

Lines from SPL-12 Records to Keep

  • Splice reports per fiber with bidirectional average loss.
  • OTDR files in the standard SR-4731 format (.sor) for both directions, named by fiber id, plus native vendor files where the owner asks for them.
  • Light source and power meter results.
  • Photos: open trays, sealed closure and labels.
  • Updated splice matrix or diagram, and the closure GPS location.

Owner-Specific Items

  • Items the owner's closeout list adds, per owner spec

Sign-Off

  • Contractor Project Manager

    • Name
    • Signature
    • Date
  • Owner Representative

    • Name
    • Signature
    • Date

From FAHMYhttps://fahmy.io/reference/templates/closeout/Version 0.2.0

FAHMY is a reference, not a substitute for owner specifications, the authority having jurisdiction, manufacturer instructions, training or qualified supervision. Follow your employer's safety program and all applicable laws.

How to Use This Sheet

The closeout package is the set of records the owner receives when the work is done. It is how the owner finds the plant again, and missing records are a common reason final payment is held. The lists on this sheet come straight from the Close Out stage and the aerial, underground and splicing closeout steps, so they stay in step with those pages.

Fill It In

  • Tick only the sections for the work on this job. An aerial-only job skips the underground and splicing records.
  • Tick an item only when the record is in the package, in the format the owner asked for.
  • Build as-builts from field redlines, bore logs and photos, never from the design.
  • Attach the signed punch list and the reconciled bill of materials.

Hand It Over

Get a signed receipt or acceptance from the owner, and keep a full copy of the package with the job file.