Contractor Name and Logo
- Project name
- Owner
- Contractor
- Work order or job number
- Area, route or segment
- Package submitted by
- Date submitted
Closeout Checklist
Lines from the Close Out stage checklist
- Field redlines turned into as-built drawings and GIS updates
- Bore logs and enclosure GPS locations included in the underground as-builts
- Tracer wire continuity tested end to end and recorded
- Test and splice reports compiled by fiber
- Splice matrix updated with every field change
- Punch list walked and cleared with the owner or inspector
- Permits closed and restoration accepted
- Pole attachment records updated with heights and transfers
- Final quantities reconciled against the BOM for invoicing
Aerial Records
Lines from AE-12 Records to Keep
- Before and after photos of every pole.
- Photos of every closure, terminal and slack location.
- Final measured attachment heights and midspan clearances.
- The owner's inspection report and proof that each punch list item was closed.
- As-builts as submitted, with the date and the owner's acceptance.
Underground Records
Lines from UG-13 Records to Keep
- As-built drawings and GIS data.
- Bore logs, pothole logs and redlines.
- Tracer wire continuity test results.
- Pull tape and cable footage at each enclosure.
- Final inspection sign-offs and permit closure letters.
- Photo archive and locate tickets.
Splicing Records
Lines from SPL-12 Records to Keep
- Splice reports per fiber with bidirectional average loss.
- OTDR files in the standard SR-4731 format (.sor) for both directions, named by fiber id, plus native vendor files where the owner asks for them.
- Light source and power meter results.
- Photos: open trays, sealed closure and labels.
- Updated splice matrix or diagram, and the closure GPS location.
Owner-Specific Items
- Items the owner's closeout list adds, per owner spec
Sign-Off
Contractor Project Manager
- Name
- Signature
- Date
Owner Representative
- Name
- Signature
- Date