AE Aerial AE-11 Step 11 of 12

Terminal Coils, Closures, Drops and Risers

Mount closures, terminals, drops and risers so they are serviceable, protected, bonded and clear of roads and the climbing space.

ChecklistOn the Map

Crew

  • Foreman
  • Lineworker
  • Splicer
  • Drop Installer
  • Ground Worker

Hazards

  • Electrical Contact
  • Falls from Ladders, Poles and Lifts
  • Struck by Vehicles
  • Contamination of Open Connector Ports

Purpose

Install closures, terminals and drops so they are serviceable, protected and clear. These are the pieces technicians come back to for years. A closure with no slack, an uncapped port or a drop hanging low over a driveway turns every service call into rework or a safety problem.

When to Do It

Roles

  • Foreman: checks locations, clearances, bonding and riser protection against the design.
  • Lineworker: mounts closure brackets, terminals, coil brackets and risers.
  • Splicer: prepares and seals closures; see the splicing SOPs.
  • Drop installer: runs drops to buildings, attaches them and bonds metallic members.
  • Ground worker: watches drops over roads and driveways and keeps the public clear.

Equipment and Materials

  • Closure mounting brackets for the strand.
  • Multiport service terminals (MSTs) or drop terminals, with connector caps in place.
  • Coil brackets for tail coils.
  • Drop clamps, drop hooks and drip loop hardware.
  • U-guard and riser conduit, and riser standoff brackets only for poles where existing risers leave no clear climbing path (NESC; owner spec).
  • Bonding and grounding hardware for the building entrance.
  • Ladder with non-conductive (fiberglass) side rails for the building attachment.

Safety

Procedure

  1. Mount aerial splice closures on the strand with brackets at the designed location.
    • Store closure slack per the design (AE-10), so the closure can be lowered for splicing.
  2. Mount MSTs or drop terminals at the designed locations.
    • Store tail coils on the pole or strand with coil brackets, keeping bend radius.
    • Keep connector caps on every unused port.
  3. Install drops from the terminal to the building.
    • Hold the drop with drop clamps at the terminal end and the building end.
    • Keep the required clearance over driveways and roads (per National Electrical Safety Code (NESC) Table 232-1 and owner spec).
    • Attach at the building with a drop hook, and form a drip loop so water runs off before the entrance.
  4. At the building, bond any metallic members of the cable per the NEC (Articles 770 and 800).
  5. Install risers where cable moves to underground.
    • Use U-guard and conduit per owner spec.
    • Protect the cable to the specified height (per owner spec).
    • Attach the riser flat to the pole face, grouped on the same side or quadrant as any existing communication risers, so the part of the pole the owner specifies stays clear for climbing (per owner or utility spec, for example 180°; NESC (IEEE C2)).
    • Use riser standoff brackets only where existing risers leave no clear climbing path (NESC (IEEE C2); owner spec).
    • Seal the conduit ends per owner spec.

Hold Points

Records to Keep

  • Closure and terminal ids and locations.
  • Drop addresses with the terminal and port used.
  • Photos of each closure, terminal, drop attachment, bond and riser.
  • Riser locations and the handhole each one feeds.

Common Mistakes

  • Low drops over driveways. Trucks and trailers catch them.
  • Uncapped terminal ports. Dirt and water in a port means cleaning or replacing it before service.
  • Risers that block the climbing space. A riser set on its own side of the pole, away from the existing communication risers, splits the clear part of the pole and can leave no clear side for the next climber.
  • Unbonded metallic members. Surges come into the building on the cable.
  • No slack at the closure, so it cannot be lowered for splicing.

Standards and References

  • NESC (IEEE C2) Table 232-1 for drop clearances.
  • NFPA 70 (NEC) Articles 770 and 800 for building entrance bonding.
  • Owner construction standards for closure, terminal, drop and riser details.
  • Closure, terminal and drop hardware manufacturer instructions.
  • 29 CFR 1910.268 for work near power.
  • OSHA 29 CFR Part 1926 for construction work, which 29 CFR 1910.268 excludes (1910.268(a)(2)(i)). Your employer’s safety program says how to comply.
  • MUTCD Part 6 for traffic control while a drop is run across a road.

On the Map

Not applicable: no FAHMY tool covers closures, terminals, drops or risers.

AE-11 · Field Checklist

Checklist

0/7items ticked

Tick each procedure step and hold point as the crew completes it. Ticks stay on this device only. They are a personal aid, not a hold-point release or a project record; follow the owner’s sign-off process.

Procedure
Hold Points

OSP Map · Route Profile

On the Map

Open the map
  • Aerial Splice ClosureSealed closure on the strand where fibers are spliced and stored.
  • Multiport Service TerminalHardened terminal with connectorized ports that customer drops plug into.
  • Terminal Tail CoilStored coil of the terminal’s tail cable, held in a bracket on the pole or strand.Drawn in the pole detail
  • Aerial DropDrop cable from a terminal to the building, held with drop clamps at each end.
  • RiserU-guard and conduit on the pole where cable moves between aerial and underground.

Report an Issue

Spotted something wrong or out of date? Emailfeedback@fahmy.iowith the step and version (AE-11, v1.0.0) and what you saw in the field.

FAHMY is a reference, not a substitute for owner specifications, the authority having jurisdiction, manufacturer instructions, training or qualified supervision. Follow your employer's safety program and all applicable laws.

Operations

More

Theme

Sunlight is maximum contrast for direct sun. Auto follows your device.